Variation Cost Report

Merrion Cross — Block C  ·  Change Register Rev 07  ·  Generated 28/05/2026

Filters

12 change itemsTotal: 243,200
Change IDDrawingDateDescriptionTradeQty ChangeWaste Est.Total CostRiskStatusAI Conf.
CHG-0041

A-301-R07

Rev 07

28/05/2026

Column grid shifted 450mm north — affects floor slab reinforcement layout

Structural+3.8 T steel0.38 T38,200
M: 22.4kL: 11.2k
CriticalPending97%
CHG-0040

M-112-R03

Rev 03

27/05/2026

AHU unit relocated from roof level to Level 4 plant room

Mechanical+18m ductwork1.2 m²24,700
M: 12.4kL: 8.9k
HighReviewing94%
CHG-0039

A-215-R07

Rev 07

27/05/2026

Partition wall added to Level 3 open-plan — 18.4m run of 100mm metal stud

Architectural+18.4m partition3.2 m²12,840
M: 6.2kL: 5.4k
LowApproved99%
CHG-0038

E-407-R05

Rev 05

26/05/2026

Additional 63A DB added to Level 2 comms room — cable tray extension required

Electrical+24m cable tray2.1m cable9,340
M: 4.8kL: 3.6k
MediumPending91%
CHG-0037

FP-061-R02

Rev 02

26/05/2026

Sprinkler head layout revised — 24 additional heads on Level 5

Fire+24 heads3.6m pipe7,000
M: 3.6kL: 2.8k
MediumPending93%
CHG-0036

S-203-R06

Rev 06

25/05/2026

Beam depth increased 450→600mm — additional 3.2T structural steel

Structural+3.2 T steel0.22 T18,900
M: 11.2kL: 5.8k
HighDisputed96%
CHG-0035

C-019-R05

Rev 05

24/05/2026

Drainage invert levels revised — 28m additional excavation and backfill

Civil+28m excavation4.2 m³14,200
M: 7.4kL: 5.2k
MediumReviewing85%
CHG-0034

P-088-R04

Rev 04

24/05/2026

Sanitary stack rerouted — 12m additional 110mm UPVC pipework

Plumbing+12m UPVC1.8m pipe5,620
M: 2.8kL: 2.2k
LowApproved88%

Showing 18 of 12 items